Status Report  Printer Friendly  Export to Excel  Export to Word  



 Filters

District
  
Community
Phase
Cycle
Sector
   
Delay
Primary Contributor
   

District
Community
Project
Phase
Cycle
Sector
Start Date
End Date
Duration
Delay
Target End Date
Status
Progress
Primary Contributor
Reasons for Delay
Actions to be Taken
Abudwak Amaano Community Action Plan 3 1 CAP 02/10/10 17/11/10 46 0 17/11/10 CAP Endorsed by Goverment 100% DFID No delay  
    Community Center 3 1 Infrastructure 02/11/10 31/05/11 210 0 31/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 23/01/11 10/05/11 107 0 10/05/11 Installment 1/1 Disbursed 100% DFID    
    Community Action Plan Updated 3 2 CAP 24/11/11 22/01/12 59   22/01/12 CAP endorsed 100% DFID_II    
    Block Grant 3 2 Not Defined 19/10/11 21/10/12 368   21/10/12 Proposal Formulation 0% DFID_II    
  Summary for Community: Amaano (5 detail records)
  Bal-howd Community Action Plan 3 1 CAP 26/10/10 17/11/10 22 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Construction of School 3 1 Education 26/10/10 30/04/11 186 0 30/04/11 Completion and Acceptance of Work 100% DFID not mensioned in the report  
    Social Services Access Grant 3 1 SAG 06/03/11 10/05/11 65 0 10/05/11 Submission of Community Final Financial Report 100% DFID    
    Block Grant 3 2 Not Defined 22/01/12 11/10/12 263   11/10/12   0% DFID_II    
    Community Action Plan Updated 3 2 CAP 23/10/11 29/11/11 37   29/11/11 CAP endorsed 0% DFID_II    
  Summary for Community: Bal-howd (5 detail records)
  Balicade Community Action Plan 3 1 CAP 27/12/10 04/01/11 8 0 04/01/11 Drafted CAP 100% DFID    
    Construction of primary and intermediate school 3 1 Education 18/11/10 31/05/11 194 0 31/05/11 Completion and Acceptance of Work 100% DFID QUA approval delay.  
    Social Services Access Grant 3 1 SAG 01/12/10 10/05/11 160 0 10/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Balicade (3 detail records)
  Bangeele Community Action Plan 3 1 CAP 31/10/10 17/11/10 17 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Construction of Health Post 3 1 Health 26/12/10 22/06/11 178 0 22/06/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 20/02/11 31/05/11 100 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Bangeele (3 detail records)
  Dhabbad Community Action Plan 3 1 CAP 26/10/10 17/11/10 22 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Construction of Health Post 3 1 Health 01/12/10 26/06/11 207 0 26/06/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 12/12/10 10/05/11 149 0 10/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Dhabbad (3 detail records)
  Galmegag Community Action Plan 3 1 CAP 06/01/11 23/01/11 17   23/01/11 CAP Endorsed by Goverment 100% DFID    
    Construction of School 3 1 Education 03/02/11 31/05/11 117 0 31/05/11 Completion and Acceptance of Work 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Social Services Access Grant 3 1 SAG 03/02/11 31/05/11 117 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Galmegag (3 detail records)
  Horsed Community Action Plan 3 1 CAP 19/10/10 17/11/10 29 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 19/11/10 10/05/11 172 0 10/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 26/12/10 31/05/11 156 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
    Market 3 2 Infrastructure 30/04/12           0% DFID    
  Summary for Community: Horsed (4 detail records)
  Kow-Luulyo Community Action Plan 3 1 CAP 26/12/10 26/12/10 0   26/12/10 CAP Endorsed by Goverment 100% DFID    
    Construction of Health Post 3 1 Health 01/11/10 31/05/11 211 0 31/05/11 Completion and Acceptance of Work 90% DFID QAU approval delay  
    Social Services Access Grant 3 1 SAG 03/02/11 31/05/11 117 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Kow-Luulyo (3 detail records)
  October Community Action Plan 3 1 CAP 02/10/10 17/11/10 46   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 02/10/10 31/05/11 241 0 31/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 21/11/10 31/05/11 191 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: October (3 detail records)
  Shiilamadow Community Action Plan 3 1 CAP 10/01/11 23/01/11 13   23/01/11 CAP Endorsed by Goverment 100% DFID    
    Construction of School 3 1 Education 01/01/11 30/05/11 149 0 30/05/11 Completion and Acceptance of Work 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Social Services Access Grant 3 1 SAG 02/02/11 31/05/11 118 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
  Summary for Community: Shiilamadow (3 detail records)
  Ubah Community Action Plan 3 1 CAP 19/10/10 17/11/10 29 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 02/11/10 31/05/11 210 0 31/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 06/02/11 31/05/11 114 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
    Block Grant 3 2 Not Defined 31/01/12         Proposal Formulation 0% DFID_II    
  Summary for Community: Ubah (4 detail records)
  Waaberi Community Action Plan 3 1 CAP 02/10/10 17/11/10 46 0 17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 02/11/10 31/05/11 210 0 31/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 09/01/11 31/05/11 142 0 31/05/11 Submission of Community Final Financial Report 100% DFID    
    Block Grant 3 2 Not Defined 01/02/12         Proposal Formulation 0% DFID_II    
    Community Action Plan Updated 3 2 CAP 02/11/11 21/11/11 19   21/11/11 CAP updated 0% DFID_II    
    Block Grant 3 2 Not Defined 19/02/12 04/06/12 106   04/06/12   0% DFID_II    
  Summary for Community: Waaberi (6 detail records)
Summary for District: Abudwak (45 detail records)
Ainabo Ainabo Hawl-wadaag Slaughter House 3 1 Infrastructure 12/12/11 05/09/12 268 0 05/09/12 MoU Signed 40% DFID_II    
    Community Action Plan 3 1 CAP 01/12/11 15/12/11 14 0 15/12/11 CAP endorsed 100% DFID_II   - To undertake the Baseline Survey in this and the next month
    Social Access Grant 3 1 SAG 18/10/11     0     0% DFID_II    
  Summary for Community: Ainabo Hawl-wadaag (3 detail records)
  Ainabo Horseed School Barrier Wall 3 1 Education 12/12/11 17/12/12 371 0 17/12/12 Installment 1/3 Disbursed 40% DFID_II No delay  
    Community Action Plan 3 1 CAP 01/12/11 15/12/11 14 0 15/12/11 Community Action Plan Drafted 0% DFID_II   CAP endorsed by Government
    Social Access Grant 3 1 SAG 18/10/11           0% DFID_II    
  Summary for Community: Ainabo Horseed (3 detail records)
  Ainabo Iftin Community Action Plan 3 1 CAP 15/11/11 30/12/11 45 0 30/12/11 Community Action Plan Drafted 100% DFID_II   CAP to be uploaded February 2012
    Block 3 1 Not Defined 28/12/11 20/11/12 328 0 20/11/12   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II    
    Community Centre 3 1 Infrastructure 30/01/12 06/09/12 220 0 06/09/12 Completion and Acceptance of Work 40% DFID_II No delay  
  Summary for Community: Ainabo Iftin (4 detail records)
  Ceelal Community Action Plan 3 1 CAP 15/02/12 29/02/12 14 0 29/02/12 CAP drafted 100% DFID_II   - To undertake the Baseline Survey in this and the next month
    Block 3 1 Not Defined 24/10/12 27/02/13 126 0 27/02/13   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Social Access Grant 3 1 SAG             0% DFID_II    
    Block Grant 3 1 Not Defined 30/01/12 11/09/12 225 0 11/09/12 Installment 3/3 Disbursed 0% DFID_II No delay  
  Summary for Community: Ceelal (4 detail records)
  Dhanaano Community Action Plan 3 1 CAP 01/02/11 15/02/11 14 0 15/02/11   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Block 3 1 Not Defined 30/01/12 16/09/12 230 0 16/09/12 Installment 3/3 Disbursed 0% DFID_II Nothing delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Dhanaano (3 detail records)
  Dhudhub Community Action Plan 3 1 CAP 01/02/12 15/02/12 14 0 15/02/12   0% DFID_II   - To finish the selection of the new communities with in this and the next month
    Block 3 1 Not Defined 30/01/12 16/09/12 230 0 16/09/12 Installment 3/3 Disbursed 0% DFID_II Nothing delay  
    Social Access Grant 3 1 SAG       0     0% DFID_II    
  Summary for Community: Dhudhub (3 detail records)
  Gadhka Community Action Plan 3 1 CAP 15/01/12 30/01/12 15 0 30/01/12   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Block 3 1 Not Defined 30/01/12 18/09/12 232 0 18/09/12 Installment 3/3 Disbursed 0% DFID_II No delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Gadhka (3 detail records)
  Gunburo Xaangeeye Community Action Plan 3 1 CAP 15/02/12 29/02/12 14 0 29/02/12   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Block 3 1 Not Defined 30/01/12 23/09/12 237 0 23/09/12 Installment 3/3 Disbursed 0% DFID_II No delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Gunburo Xaangeeye (3 detail records)
  Habari-heshay Community Action Plan 3 1 CAP 15/12/11 30/12/10 -350 0 30/12/10   0% DFID_II   - To finish the selection of the new communities with in this and the next month
    School construction 3 1 Education 30/01/12 24/09/12 238 0 24/09/12 Installment 3/3 Disbursed 40% DFID_II   - To finish the selection of the new communities with in this and the next month
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II    
  Summary for Community: Habari-heshay (3 detail records)
  Higlo Community Action Plan 3 1 CAP 01/01/12 15/01/12 14 0 15/01/12   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Community Centre 3 1 Infrastructure 30/01/12 25/09/12 239 0 25/09/12 Installment 3/3 Disbursed 0% DFID_II    
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Higlo (3 detail records)
  Oog Community Action Plan 3 1 CAP 15/02/12 29/02/12 14 0 29/02/12   0% DFID_II    
    Block 3 1 Not Defined 30/01/12 26/09/12 240 0 26/09/12 Installment 3/3 Disbursed 0% DFID_II    
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II    
  Summary for Community: Oog (3 detail records)
  Qoridheere Community Action Plan 3 1 CAP 01/01/12 15/01/12 14 0 15/01/12   0% DFID_II   - To undertake the Baseline Survey in this and the next month
    Block 3 1 Not Defined 30/01/12 27/09/12 241 0 27/09/12 Installment 3/3 Disbursed 0% DFID_II Nothing delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Qoridheere (3 detail records)
  Wadaamagoo Community Action Plan 3 1 CAP 15/12/11 30/12/11 15 0 30/12/11   0% DFID_II   - To finish the selection of the new communities with in this and the next month
    Community Market 3 1 Income Generation 30/01/12 01/10/12 245 0 01/10/12 Installment 3/3 Disbursed 40% DFID_II No delay - To finish the selection of the new communities with in this and the next month
    Social Access Grant 3 1 SAG 00/00/00     0     0% DFID_II    
  Summary for Community: Wadaamagoo (3 detail records)
  War'idaad Community Action Plan 3 1 CAP 01/01/12 15/01/12 14 0 15/01/12   0% DFID_II   - To finish the selection of the new communities with in this and the next month
    Community Centre 3 1 Infrastructure 30/01/12 02/10/12 246 0 02/10/12 Installment 3/3 Disbursed 40% DFID_II No delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: War'idaad (3 detail records)
  Wiriir Community Action Plan 0 0 CAP 15/01/12 30/01/12 15 0 30/01/12   0% DFID_II   - To finish the selection of the new communities with in this and the next month
    Community Centre 3 1 Infrastructure 30/01/12 03/10/12 247 0 03/10/12 Completion and Acceptance of Work 40% DFID_II No delay  
    Social Access Grant 3 1 SAG             0% DFID_II    
  Summary for Community: Wiriir (3 detail records)
Summary for District: Ainabo (47 detail records)
Beletweyne Bacaad commmunity action plan 2 1 CAP 03/12/09 14/12/09 11 106 30/03/10 CAP reviewed by partners 100% WB    
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 58 27/09/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 15/08/10 227 86 09/11/10 Completion and Acceptance of work 100% WB    
    Social Services Access Grant(additional funding) 2 1 SAG 26/04/11     0   Installment 1/1 disbursed 100% WB    
  Summary for Community: Bacaad (4 detail records)
  Beerxaano Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 84 08/03/10 CAP reviewed by partners 100% WB    
    Socail Access Grant 2 1 SAG 15/12/09 31/07/10 228 0 31/07/10 Submission of Community Final Report 100% WB    
    Construction of Marketplace 2 1 Infrastructure 31/12/09 15/08/10 227 86 09/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Beerxaano (3 detail records)
  Caagsibiri community action plan 2 1 CAP 03/12/09 14/12/09 11 99 23/03/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 34 03/09/10 Submission of Community Final Report 100% WB    
    Construction of School 2 1 Education 31/12/09 30/09/10 273 56 25/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Caagsibiri (3 detail records)
  Caloolacad Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 76 28/02/10 CAP endorsed by gov 100% WB    
    Social Access Grant 2 1 SAG 15/12/09 31/07/09 -137 0 31/07/09 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 15/08/10 227 86 09/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Caloolacad (3 detail records)
  Camaloow Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 0 31/07/10 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 76 28/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 15/08/10 227 86 09/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Camaloow (3 detail records)
  Dharkeynta Community action plan 2 1 CAP 03/12/09 14/12/09 11 209 11/07/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Socail Access Grant 2 1 SAG 15/12/09 31/07/10 228 0 31/07/10 Submission of Community Final Report 100% WB    
    School construction 2 1 Education 31/12/09 15/08/10 227 89 12/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Dharkeynta (3 detail records)
  El Aali Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 76 28/02/10   0% WB    
    Social Access Fund 2 1 SAG 15/01/10 31/07/10 197 96 04/11/10 Submission of Community Final Report 100% WB    
    Community Center 2 1 Infrastructure 31/01/10 30/09/10 242 56 25/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: El Aali (3 detail records)
  Farlibaax community action plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 72 11/10/10 Submission of Community Final Report 100% WB    
    Community Center 2 1 Infrastructure 31/01/10 30/09/10 242 75 14/12/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Farlibaax (3 detail records)
  Geedlabenaad Community Action plan 2 1 CAP 03/12/09 14/12/09 11 76 28/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Socail access Grant 2 1 SAG 15/12/09 31/07/10 228 0 31/07/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 30/09/10 273 52 21/11/10 Submission of Community Final Report 100% WB    
  Summary for Community: Geedlabenaad (3 detail records)
  Hiraan Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 76 28/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Socail Access grant 2 1 SAG 15/12/09 31/07/09 -137 0 31/07/09 Submission of Community Final Report 100% WB    
    Health post 2 1 Health 31/12/09 15/08/10 227 89 12/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Hiraan (3 detail records)
  Hoyin community action plan 2 1 CAP 21/11/09 02/12/09 11 88 28/02/10 CAP endorsed by traditional leaders-Ugas 100% DANIDA    
    Social Access Grant 2 1 SAG 15/01/09 31/07/10 562 0 31/07/10 Submission of Community Final Report 100% DANIDA    
    Health post 2 1 Health 31/01/09 30/09/10 607 89 28/12/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Hoyin (3 detail records)
  Ilkacado Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% DANIDA    
    Social Access Grant 2 1 SAG 31/01/10 31/07/10 181 0 31/07/10 Submission of Community Final Report 100% DANIDA    
    Constuction of Two Berkads 2 1 Water Supply 31/01/10 30/09/10 242 52 21/11/10 Submission of Community Final Report 100% DANIDA    
  Summary for Community: Ilkacado (3 detail records)
  Jaadle Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 184 16/06/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/01/10 31/07/10 197 0 31/07/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 30/09/10 242 52 21/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Jaadle (3 detail records)
  Jawiil Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% DANIDA    
    Social Access Fund 2 1 SAG 31/01/10 31/07/10 181 0 31/07/10 Submission of Community Final Report 100% DANIDA    
    Marketplace 2 1 Infrastructure 31/01/10 30/09/10 242 52 21/11/10 Completion and Acceptance of work 100% DANIDA    
  Summary for Community: Jawiil (3 detail records)
  Macaan qaal community action plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Fund 2 1 SAG 15/01/10 31/07/10 197 0 31/07/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Water Supply 31/01/10 30/09/10 242 52 21/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Macaan qaal (3 detail records)
  Qoolaaw Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/01/10 31/07/10 197 0 31/07/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 30/09/10 242 52 21/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Qoolaaw (3 detail records)
  Qoydo Socail Access Grant 2 1 SAG 15/01/10 31/07/10 197 0 31/07/10 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 99 23/03/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Contruction of Irrigation System 2 1 Water Supply 15/01/10 30/09/10 258 52 21/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Qoydo (3 detail records)
  Quracleey Community Action plan 2 1 CAP 03/12/09 14/12/09 11 77 01/03/10 CAP endorsed by traditional leaders-Ugas 100% DANIDA    
    Socail Access Grant 2 1 SAG 15/01/10 31/07/10 197 0 31/07/10 Submission of Community Final Report 100% DANIDA    
    Construction of Primary School 2 1 Education 15/01/10 30/09/10 258 52 21/11/10 Completion and Acceptance of work 100% DANIDA    
  Summary for Community: Quracleey (3 detail records)
  Raangaabo community Action plan 2 1 CAP 03/12/09 15/12/09 12 75 28/02/10 CAP endorsed by traditional leaders-Ugas 100% DANIDA    
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 77 16/10/10 Submission of Community Final Report 100% DANIDA    
    School extention 2 1 Education 31/12/09 15/08/10 227 88 11/11/10 Completion and Acceptance of work 100% DANIDA    
  Summary for Community: Raangaabo (3 detail records)
  Sugoow Community Action Plan 2 1 CAP 03/12/09 14/12/09 11 75 27/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/01/10 31/07/10 197 54 23/09/10 Submission of Community Final Report 100% WB    
    Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 30/09/10 242 54 23/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Sugoow (3 detail records)
  Trejante Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 76 16/02/10 CAP endorsed by traditional leaders-Ugas 100% WB    
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 228 77 16/10/10 Submission of Community Final Report 100% WB    
    Health post 2 1 Health 31/12/09 15/08/10 227 88 11/11/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Trejante (3 detail records)
Summary for District: Beletweyne (64 detail records)
Berbera Abdal Market 1 1 Infrastructure 17/04/08 14/02/09 303 0 14/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 09/05/09 14/05/09 5 3 17/05/09 CAP endorsed by Government 100% WB    
    Maternal and Child Health Center (MCH) 2 2 Health 14/03/09 15/10/09 215 54 08/12/09 Submission of Community Final Report 100% WB    
  Summary for Community: Abdal (4 detail records)
  Barwaqo Community Revolving Fund 1 1 Income Generation 16/04/08 14/02/09 304 0 14/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 30/04/09 136 0 30/04/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 12/08/09 12/08/09 0 0 12/08/09 CAP endorsed by Government 100% WB    
    Construction of Cummunity Center 2 2 Infrastructure 23/09/09 30/06/10 280 5 05/07/10 Submission of Community Final Report 100% WB    
  Summary for Community: Barwaqo (4 detail records)
  Burao Sheik Social Access Fund 1 1 SAG 15/12/08 27/03/09 102 0 27/03/09 Submission of Community Final Report 100% WB    
    Community Centre 2 2 Infrastructure 09/04/09 09/01/10 275 97 16/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 09/04/09 14/04/09 5 0 14/04/09 CAP endorsed by Government 100% WB    
  Summary for Community: Burao Sheik (3 detail records)
  Daroleh Community Centre 1 1 Infrastructure 15/04/08 21/02/09 312 0 21/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Revolving Fund 2 2 Income Generation 11/04/09 11/02/10 306 69 21/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 11/04/09 16/04/09 5 0 16/04/09 CAP endorsed by Government 100% WB    
  Summary for Community: Daroleh (4 detail records)
  Doha Guban Irrigation System 1 1 Agriculture Extension 17/04/08 28/02/09 317 0 28/02/09 Submission of Community Final Report 100% WB    
    Health Post 1 1 Health 17/04/08 19/03/09 336 0 19/03/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 11/03/09 86 0 11/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 13/05/09 18/05/09 5 0 18/05/09 CAP endorsed by Government 100% WB    
    Extention of Irrigation system 2 2 Agriculture Extension 17/05/09 30/06/10 409 97 05/10/10 Submission of Community Final Report 100% WB    
  Summary for Community: Doha Guban (5 detail records)
  Lafarug Community Marketplace 1 1 Infrastructure 16/04/08 16/04/09 365 0 16/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 11/05/09 16/05/09 5 1 17/05/09 CAP endorsed by Government 100% WB    
    Peace Center 2 2 Infrastructure 02/06/09 31/05/10 363 53 23/07/10 Submission of Community Final Report 100% WB    
  Summary for Community: Lafarug (4 detail records)
  Lalays Water diversion 1 1 Environment 16/04/08 28/02/09 318 0 28/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 11/03/09 86 0 11/03/09 Submission of Community Final Report 100% WB    
    Primary School extension 2 2 Education 23/04/09 31/05/10 403 0 31/05/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 11/05/09 16/05/09 5 0 16/05/09 CAP endorsed by Government 100% WB    
  Summary for Community: Lalays (4 detail records)
  Las'idle Health Post 1 1 Health 16/04/08 10/02/09 300 0 10/02/09 Submission of Community Final Report 100% WB    
    Community Revolving Fund 1 1 Income Generation 17/04/08 27/02/09 316 0 27/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 27/03/09 102 0 27/03/09 Submission of Community Final Report 100% WB    
    Community Centre 2 2 Infrastructure 23/04/09 31/05/10 403 94 02/09/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 15/04/09 20/04/09 5 0 20/04/09 CAP endorsed by Government 100% WB    
    Electricity 2 2 Infrastructure 15/04/09 30/06/10 441 120 28/10/10 Submission of Community Final Report 100% WB    
    School extension (Additional Funding) 2 3 Education 15/05/10 30/09/10 138 0 30/09/10 Completion and Acceptance of work 100% WB    
    Social Access Fund (Additional funding) 2 3 SAG 15/05/10 30/09/10 138 0 30/09/10 Submission of Community Final Report 100% WB    
  Summary for Community: Las'idle (8 detail records)
  Tulio Dhibijo Community Latrines 1 1 Sanitation 15/03/08 29/04/09 410 0 29/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 27/03/09 102 0 27/03/09 Submission of Community Final Report 100% WB    
    Health post and community center 2 2 Health 15/04/09 22/03/10 341 127 27/07/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 16/05/09 21/05/09 5 0 21/05/09 CAP endorsed by Government 100% WB    
  Summary for Community: Tulio Dhibijo (4 detail records)
  Wadajir Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Revolving Fund 1 2 Income Generation 15/04/08 14/02/09 305 0 14/02/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 09/05/09 14/05/09 5 0 14/05/09 CAP endorsed by Government 100% WB    
    Community centre 2 2 Infrastructure 02/06/09 04/02/10 247 126 10/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Wadajir (4 detail records)
Summary for District: Berbera (44 detail records)
Boroma Abu Qyas Health Post 1 1 Health 17/04/08 21/02/09 310 0 21/02/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 26/04/09 132 0 26/04/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 31/07/09 05/08/09 5 87 31/10/09 CAP endorsed by Government 100% WB    
    Water catchment (Dam) 2 2 Water Supply 16/08/09 31/05/10 288 95 03/09/10 Submission of Community Final Report 100% WB    
    Farm Bunds 2 2 Agriculture Extension 16/08/09 31/05/10 288 95 03/09/10 Submission of Community Final Report 100% WB    
  Summary for Community: Abu Qyas (5 detail records)
  Ceelabaxay Irrigation System 1 1 Agriculture Extension 16/04/08 09/04/09 358 0 09/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 10/04/09 116 0 10/04/09 Submission of Community Final Report 100% WB    
    Irrigation Extension 2 2 Agriculture Extension 31/05/09 01/12/09 184 115 26/03/10 Submission of Community Final Report 100% WB    
    Gabions for soil erosion control 2 2 Environment 31/05/09 01/12/09 184 137 17/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 28/04/09 03/05/09 5 13 16/05/09 CAP endorsed by Government 100% WB    
  Summary for Community: Ceelabaxay (5 detail records)
  Holhol Social Access Fund 1 1 SAG 15/12/08 31/03/09 106 0 31/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 28/04/09 03/05/09 5 13 16/05/09 CAP endorsed by Government 100% WB    
    MCH 2 2 Health 09/08/09 31/05/10 295 76 15/08/10 Submission of Community Final Report 100% WB    
  Summary for Community: Holhol (3 detail records)
  Jir Jir Health Post 1 1 Health 16/04/08 24/03/09 342 0 24/03/09 Submission of Community Final Report 100% WB   cmt: Strong winds blew off the roof of the h/post in March 2010 and the CDC rapidly mobilized the community and raised the $600 required to repair the roof within 5 days. This saved the building from further destruction by the heavy rains at the time.
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 16/05/09 21/05/09 5 87 16/08/09 CAP endorsed by Government 100% WB    
    Community Revolving Funds 2 2 Income Generation 24/06/09 21/03/10 270 51 11/05/10 Submission of Community Final Report 100% WB severe droughts that led to out migrations from the village; lack of commitment by some grantees the last 09 grantees were obtained loans on Sept 1. The community is still to decide whether to continue with the RF or select another subproject once all funds will be collected from grantees.
  Summary for Community: Jir Jir (4 detail records)
  Qalooc Berkeds 1 1 Water Supply 17/04/08 23/04/09 371 0 23/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 21/04/09 26/04/09 5 20 16/05/09 CAP endorsed by Government 100% WB    
    Berkeds 2 2 Water Supply 03/05/09 15/10/09 165 34 18/11/09 Submission of Community Final Report 100% WB    
    2 Barkeds (Additional funding) 2 3 Water Supply 15/05/10 30/09/10 138 0 30/09/10 Completion and Acceptance of work 100% WB    
    Social Access Fund (Additional Funding) 2 3 SAG 15/05/10 30/09/10 138 0 30/09/10 Installment 1/1 disbursed 100% WB    
  Summary for Community: Qalooc (6 detail records)
  Sh. Ahmed Salan Community Marketplace 1 1 Infrastructure 15/04/08 26/03/09 345 45 10/05/09 Submission of Community Final Report 100% WB   the large crack in the market wall and foundation was repaired with additional funding from DRC. The market was scheduled to go operational after the 2010 Ramadan celebrations in Sept.
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 11/05/09 16/05/09 5 94 18/08/09 CAP endorsed by Government 100% WB    
    Community Revolving Fund 2 2 Income Generation 11/05/09 21/03/10 314 41 01/05/10 Completion and Acceptance of work 100% WB   cmt1:though the community plan to continue with the revolving funds, they decided to use 800 usd from the revolving fund as community contribution for the repairs of the cycle 1 marketplace.
  Summary for Community: Sh. Ahmed Salan (4 detail records)
  Sh. Ali Jawar Latrines 1 1 Sanitation 15/04/08 23/04/09 373 0 23/04/09 Submission of Community Final Report 100% WB   one of the 40 latrines collapsed, the community dug the hole but awaits DRC to help build the superstructure
    Social Access Fund 1 1 SAG 15/12/08 31/03/09 106 0 31/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 25/04/09 30/04/09 5 16 16/05/09 CAP endorsed by Government 100% WB    
    Community Revolving Fund 2 2 Income Generation 25/04/09 30/06/10 431 29 29/07/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Sh. Ali Jawar (4 detail records)
  Sh. Makhail Extension of Primary School 1 1 Education 15/04/08 27/04/09 377 0 27/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 30/04/09 136 0 30/04/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 29/04/09 04/05/09 5 12 16/05/09 CAP endorsed by Government 100% WB    
    Community Revolving Fund 2 2 Income Generation 29/04/09 30/06/10 427 29 29/07/10 Completion and Acceptance of work 100% WB    
  Summary for Community: Sh. Makhail (4 detail records)
  Sh. Osman Footbridge and Irish Crossing 1 1 Infrastructure 15/04/08 09/03/09 328 0 09/03/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 94 0 19/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 25/04/09 30/04/09 5 16 16/05/09 CAP endorsed by Government 100% WB    
    Community Revolving Fund 2 2 Income Generation 25/04/09 30/06/10 431 14 14/07/10 Submission of Community Final Report 100% WB   cmt1: when all revolving funds will be collected, the community plans to use the funds to expand the footbridge
  Summary for Community: Sh. Osman (4 detail records)
  Tulli Berkeds 1 1 Water Supply 17/04/08 30/04/09 378 0 30/04/09 Submission of Community Final Report 100% WB   as of July 2010, the two berkads had cracks and were not holding water. The community will use their O_M plan to repair the berkads.
    Social Access Fund 1 1 SAG 15/12/08 31/03/09 106 0 31/03/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 19/04/09 24/04/09 5 22 16/05/09 CAP endorsed by Government 100% WB    
    Berkeds 2 2 Water Supply 03/05/09 15/10/09 165 30 14/11/09 Submission of Community Final Report 100% WB    
  Summary for Community: Tulli (4 detail records)
Summary for District: Boroma (43 detail records)
Bossaso Afur-ur Health Post 1 1 Health 09/05/08 11/04/09 337 0 11/04/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 25/01/08 15/06/09 507 0 15/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 08/01/09 31/07/09 204 0 31/07/09 CAP endorsed by Government 100% WB    
    Community hall 2 2 Infrastructure 04/05/09 31/12/09 241 0 31/12/09 Submission of Community Final Report 100% WB    
  Summary for Community: Afur-ur (4 detail records)
  Girible Health Post 1 1 Health 09/05/08 30/06/09 417 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 23/12/08 30/06/09 189 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 11/07/09 16/07/09 5 0 16/07/09 CAP endorsed by Government 100% WB    
    Marketplace 2 2 Infrastructure 12/08/09 29/06/10 321 52 20/08/10 Submission of Community Final Report 100% WB    
  Summary for Community: Girible (4 detail records)
  Hafatul Arab Health Post 1 1 Health 11/05/08 30/06/09 415 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 23/12/08 30/06/09 189 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 07/07/09 12/07/09 5 0 12/07/09 CAP endorsed by Government 100% WB    
    Construction of School 2 2 Education 12/08/09 29/06/10 321 0 29/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Hafatul Arab (4 detail records)
  Kalabayr School 1 1 Education 11/05/08 30/06/09 415 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 23/12/08 30/06/09 189 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 13/07/09 18/07/09 5 0 18/07/09 CAP endorsed by Government 100% WB    
    School Extension 2 2 Education 12/08/09 30/06/10 322 0 30/06/10 Completion and Acceptance of work 100% WB    
    Community Centre 2 2 Infrastructure 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Kalabayr (5 detail records)
  Karin Latrine 1 1 Sanitation 11/12/08 30/06/09 201 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 25/01/09 30/06/09 156 0 30/06/09 Submission of Community Final Report 100% WB    
    Wells and Barkads 2 2 Agriculture Extension 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 14/07/09 19/07/09 5 0 19/07/09 CAP endorsed by Government 100% WB    
  Summary for Community: Karin (4 detail records)
  Laag Extension of School 1 1 Education 29/03/09 30/06/09 93 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 23/12/08 30/06/09 189 0 30/06/09 Submission of Community Final Report 100% WB    
    School Extension 2 2 Education 12/08/09 30/06/10 322 0 30/06/10 Completion and Acceptance of work 100% WB    
    Community Action Plan Updated 2 2 CAP 14/07/09 19/07/09 5 0 19/07/09 CAP endorsed by Government 100% WB    
    Water Extension 2 2 Water Supply 12/01/10     0   Submission of Community Final Report 100% WB    
  Summary for Community: Laag (5 detail records)
  Reebi Health Post 1 1 Health 09/05/08 31/03/09 326 0 31/03/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 22/12/08 30/06/09 190 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 07/07/09 12/07/09 5 0 12/07/09 CAP endorsed by Government 100% WB    
    Marketplace 2 2 Infrastructure 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Reebi (4 detail records)
  Soweto Health Post 1 1 Health 12/05/08 30/06/09 414 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 19/12/08 30/06/09 193 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 17/07/09 22/07/09 5 0 22/07/09 CAP endorsed by Government 100% WB    
    Garbage Collection Pits 2 2 Sanitation 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Soweto (4 detail records)
  Tasjic Water System 1 1 Water Supply 11/12/08 30/06/09 201 0 30/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 25/01/09 30/06/09 156 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 26/07/09 31/07/09 5 0 31/07/09 CAP endorsed by Government 100% WB    
    Extention of School 2 2 Education 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Center (Additional funding) 2 3 Infrastructure 15/05/10 30/09/10 138 30 30/10/10 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Social Access Fund (Additional Funding) 2 3 SAG 15/05/10 30/09/10 138 30 30/10/10 Submission of Community Final Report 100% WB    
  Summary for Community: Tasjic (6 detail records)
  Yalho Health Post 1 1 Health 15/05/08 15/06/09 396 0 15/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 1 1 SAG 22/12/08 30/06/09 190 0 30/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 2 2 CAP 09/07/09 09/07/09 0 0 09/07/09 CAP updated 100% WB    
    School Extension 2 2 Education 12/08/09 30/06/10 322 0 30/06/10 Submission of Community Final Report 100% WB    
  Summary for Community: Yalho (4 detail records)
Summary for District: Bossaso (44 detail records)
Ceelafweyn Beerweyso 2nd Barket 0 0 Water Supply 04/04/12           50% DANIDA    
    Community Action Plan 3 1 CAP 08/03/11 30/11/11 267 0 30/11/11 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Berked construction 3 1 Water Supply 01/06/11 30/11/11 182 0 30/11/11 Installment 3/3 Disbursed 100% DANIDA_RPLP    
    Community Center 3 1 Infrastructure 01/06/11 30/11/11 182 0 30/11/11 Installment 3/3 Disbursed 100% DANIDA_RPLP    
    Latrine construction 3 1 Sanitation 04/04/12           100% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81 0 29/02/12   0% DFID_II completing Cycle I  
    Block Grant 3 2 Not Defined 12/02/12 31/10/12 262   31/10/12   0% DFID_II    
  Summary for Community: Beerweyso (7 detail records)
  Bixin Community Action Plan 2 1 CAP 01/01/09 02/01/09 1 0 02/01/09 Drafted CAP 100% DANIDA_PLIS    
    Canal Extension 2 1 Water Supply 01/10/09 28/02/10 150 0 28/02/10 Completion and Acceptance of work 100% DANIDA_PLIS    
  Summary for Community: Bixin (2 detail records)
  Bohol Community Action Plan 2 1 CAP 01/01/09 01/01/09 0 0 01/01/09 CAP Endorsed by Goverment 100% DANIDA_PLIS    
    Construction of two Barkads 2 1 Water Supply 01/10/09 28/02/10 150 0 28/02/10 Submission of Community Final Report 100% DANIDA_PLIS    
  Summary for Community: Bohol (2 detail records)
  Ceelafwayn town Community Action Plan 2 1 CAP 01/01/09 02/01/09 1 0 02/01/09 CAP Endorsed by Goverment 100% DANIDA_PLIS   Support discontinued
    Construction of roof catchment 2 1 Water Supply 02/02/09 31/10/10 636 0 31/10/10 Submission of Community Final Report 100% Not Defined   Support discontinued
    20 Roof Catchments with Berkads 3 1 Water Supply 01/01/10 31/05/11 515 0 31/05/11 Completion and Acceptance of work 100% DANIDA_RPLP   Support discontinued
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81 0 29/02/12   0% DFID_II completing Cycle I  
    Roof catchments 3 2 Water Supply 12/02/12 31/10/12 262   31/10/12   40% DFID_II    
  Summary for Community: Ceelafwayn town (5 detail records)
  Ceellahelay Community Action Plan 3 1 CAP 08/03/11 31/12/11 298 0 31/12/11 CAP Endorsed by Goverment 0% DANIDA_RPLP    
    1 big Barkad and 7 roof catchments 3 1 Water Supply 01/05/11 30/12/11 243 0 30/12/11 Installment 3/3 Disbursed 0% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81 0 29/02/12   0% SIDA completing Cycle I  
    Community Centre 3 2 Infrastructure 12/02/12 31/10/12 262   31/10/12   40% DFID_II    
    Community Centre 3 2 Infrastructure 09/05/12           0% DFID_II    
  Summary for Community: Ceellahelay (5 detail records)
  Ceelmidgaan Cinstruction if barkad 0 0 Water Supply 09/04/12           0% Not Defined    
    Community Action Plan 3 1 CAP 08/03/11 30/11/11 267 0 30/11/11   0% DANIDA_RPLP    
    School construction 3 1 Education 16/08/11     0   Installment 1/3 Disbursed 100% DANIDA_RPLP Staff Responsibly has changed  
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81 0 29/02/12   0% DFID_II completing Cycle I  
    Block Grant 3 2 Not Defined 12/02/12 31/10/12 262   31/10/12   0% DFID_II    
  Summary for Community: Ceelmidgaan (5 detail records)
  Dararweyne Community Action Plan 2 1 CAP 01/01/09 30/01/09 29 0 30/01/09 Drafted CAP 100% DANIDA_PLIS    
    Community Center 2 1 Infrastructure 01/10/09 28/02/10 150 0 28/02/10 Completion and Acceptance of work 100% DANIDA_PLIS    
  Summary for Community: Dararweyne (2 detail records)
  Dhabarmamac Community Action Plan 2 1 CAP 01/01/09 01/01/09 0 0 01/01/09 CAP Endorsed by Goverment 100% DANIDA_PLIS    
    Construction of two Barkads 2 1 Water Supply 06/03/11 28/02/10 -371 0 28/02/10 Completion and Acceptance of work 100% DANIDA_PLIS    
    Community Action Plan Updated 3 2 CAP 14/02/12         CAP updated 0% EC    
  Summary for Community: Dhabarmamac (3 detail records)
  Doqoble Community Action Plan 2 1 CAP 01/01/09 30/01/09 29 0 30/01/09 CAP Endorsed by Goverment 100% DANIDA_PLIS    
    Construction of two Barkads 2 1 Water Supply 01/10/09 28/02/10 150 0 28/02/10 Completion and Acceptance of work 100% DANIDA_PLIS    
  Summary for Community: Doqoble (2 detail records)
  Gal iyo Qac Community Action Plan 3 1 CAP 08/03/11 31/12/11 298 0 31/12/11   0% DANIDA_RPLP   The second payment processed October 2011
    Berkad construction 3 1 Water Supply 03/07/11 31/12/11 181 0 31/12/11 Installment 3/3 Disbursed 0% DANIDA_RPLP   The second payment processed October 2011
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81 0 29/02/12   0% DFID_II completing Cycle I  
    Block Grant 3 2 Not Defined 12/02/12 31/10/12 262   31/10/12   0% DFID_II    
    Berkad construction 3 2 Water Supply 09/05/12           60% DFID_II    
  Summary for Community: Gal iyo Qac (5 detail records)
  Garabcad Community Center 0 0 Infrastructure 09/04/12     0     50% Not Defined   Spend more time having meetings with concerned coordinators and finalized this month.
    Community Action Plan 3 1 CAP 08/03/11 15/04/11 38 0 15/04/11 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Berkads 3 1 Water Supply 12/05/11 31/12/11 233 0 31/12/11 Completion and Acceptance of Work 0% DANIDA_RPLP   Prolonged technical review
    Community Action Plan Updated 3 2 CAP 10/12/11 29/12/12 385 0 29/12/12   0% DFID_II completing Cycle I  
    Community Centre 3 2 Infrastructure 12/02/12 31/10/12 262   31/10/12   40% DFID_II    
  Summary for Community: Garabcad (5 detail records)
  God caanood Community Action Plan 3 1 CAP 26/09/10 31/05/11 247 0 31/05/11 Drafted CAP 100% DANIDA_RPLP    
    Berkad and Irrigation Canal 3 1 Agriculture Extension 26/09/10 21/02/11 148 0 21/02/11 Completion and Acceptance of work 100% DANIDA_RPLP    
    Community Action Plan Updated 3 2 Not Defined 10/12/11 29/02/12 81 0 29/02/12   0% DFID_II completing Cycle I  
    Classroom construction 3 2 Education 12/02/12 31/10/12 262 0 31/10/12   40% DFID_II no delay  
    Construction of 2 classrooms 3 2 Education 05/02/12 27/02/12 22 0 27/02/12 2/3 installment 80% DFID_II No delay  
  Summary for Community: God caanood (5 detail records)
  Hamilka Barkats 2 1 Water Supply 01/10/09 28/02/10 150 0 28/02/10 Submission of Community Final Report 100% DANIDA_PLIS    
    Community Action Plan 2 1 CAP 01/01/09 30/01/09 29 0 30/01/09 CAP Endorsed by Goverment 100% DANIDA_PLIS    
    Community Action Plan Updated 3 2 CAP 14/02/12         CAP updated 0% EC    
  Summary for Community: Hamilka (3 detail records)
  Huluul Community Action Plan 3 1 CAP 26/09/10 31/05/11 247 0 31/05/11 Drafted CAP 100% DANIDA_RPLP   Support discontinued
    School Extension 3 1 Education 26/09/10 31/05/11 247 0 31/05/11 Installment 2/3 disbursed 100% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 30/01/12     0     0% DFID_II completing Cycle I  
    Block Grant 3 2 Not Defined 12/02/12 31/10/12 262   31/10/12   0% DFID_II    
  Summary for Community: Huluul (4 detail records)
  Kalsheik Construction of 2 classrooms 1 3 Education 08/05/12           0% Not Defined    
    Community Action Plan 3 1 CAP 26/09/10 31/05/11 247 0 31/05/11 Drafted CAP 100% DANIDA_RPLP    
    School Extension 3 1 Education 26/09/10 31/05/11 247 0 31/05/11 Completion and Acceptance of work 100% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 10/12/11 10/12/11 0   10/12/11   0% DFID_II    
    Community Centre 3 2 Education 12/02/12 31/10/12 262 0 31/10/12   40% DFID_II    
    Community Centre 3 2 Infrastructure 02/02/12 30/07/12 179   30/07/12   90% DFID_II    
  Summary for Community: Kalsheik (6 detail records)
  Sin-Caro Community Action Plan 3 1 CAP 26/09/10 31/05/11 247 0 31/05/11 Drafted CAP 100% DANIDA_RPLP    
    School Extension 3 1 Education 26/09/10 31/05/11 247 0 31/05/11 Completion and Acceptance of work 100% DANIDA_RPLP To undertake the CSA  
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 81   29/02/12   0% DFID_II    
    Block Grant 3 2 Not Defined 12/02/12 31/10/12 262 0 31/10/12   0% DFID_II no delay  
  Summary for Community: Sin-Caro (4 detail records)
Summary for District: Ceelafweyn (65 detail records)
North_Galkayo Agaaran Community Centre 2 1 Infrastructure 15/02/09 28/04/10 437 0 28/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 17/04/09 27/05/09 40 18 14/06/09 Endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 29/10/09 10/05/10 193 0 10/05/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 11/09/11 03/10/11 22 0 03/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Market place 3 2 Infrastructure 17/10/11 27/08/12 315 0 27/08/12   0% SIDA All activities covered under minimal constraints  
  Summary for Community: Agaaran (5 detail records)
  Baadweyn Three Garbage Collection Sites 2 1 Sanitation 25/03/09 25/01/10 306 60 26/03/10 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 25/03/09 04/05/09 40 41 14/06/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community center (Additional funding) 2 1 Infrastructure 15/05/10 30/09/10 138 0 30/09/10 Completion and Acceptance of work 100% WB   - To upload the documents in late October and early November 2011
    Social Access Fund (Additional funding) 2 1 SAG 15/05/10 30/09/10 138 0 30/09/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 17/09/11 03/10/11 16 0 03/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    School extension 3 2 Not Defined 24/10/11 29/07/12 279 0 29/07/12   0% SIDA All activities covered under minimal constraints.  
  Summary for Community: Baadweyn (7 detail records)
  Beyra Water Cistern and Three Troughs 2 1 Water Supply 25/03/09 25/03/09 0 84 17/06/09 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 25/03/09 04/05/09 40 41 14/06/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 19/09/11 06/10/11 17 0 06/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    School extension 3 2 Education 31/10/11 31/07/12 274 0 31/07/12   0% SIDA All activities covered under minimal constraints.  
  Summary for Community: Beyra (5 detail records)
  Bursaleh Community Action Plan 2 1 CAP 25/01/09 06/03/09 40 88 02/06/09 CAP endorsed by gov 100% WB    
    Construction of Assembly hall 2 1 Infrastructure 12/08/09 29/04/09 -105 48 16/06/09 Submission of Community Final Report 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 18/09/11 11/10/11 23 0 11/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Garbage Pits construction 3 2 Not Defined 08/11/11 02/08/11 -98 0 02/08/11   0% SIDA All activities covered under minimal constraints  
  Summary for Community: Bursaleh (5 detail records)
  Garsoor 1 Community Centre 2 1 Infrastructure 12/08/09 30/06/10 322 48 17/08/10 Submission of Community Final Report 100% WB    
    Community Action Plan 2 1 CAP 04/02/09 16/03/09 40 117 11/07/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 11/09/11 28/09/11 17 0 28/09/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Market place 3 2 Infrastructure 17/10/11 19/08/12 307 0 19/08/12   0% SIDA All activities covered under minimal constraints  
  Summary for Community: Garsoor 1 (5 detail records)
  Garsoor 2 Community Market Place 3 2 Infrastructure 24/11/10 30/03/11 126 70 08/06/11 Installment 1/3 Disbursed 0% DANIDA_RPLP -Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions. - To start construction, - To collect the financial reports after the CPIU confirms the progress
    Community Action Plan Updated 3 2 CAP 19/10/10 21/10/10 2 0 21/10/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
  Summary for Community: Garsoor 2 (2 detail records)
  Garsoor 3 Community Action Plan Updated 3 2 CAP 11/05/11 11/05/11 0   11/05/11 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Community Market Place 3 2 Infrastructure 06/12/10 05/04/11 120 0 05/04/11 Installment 1/3 Disbursed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
  Summary for Community: Garsoor 3 (2 detail records)
  Garsoor 4 Community Action Plan 2 1 CAP 01/07/09 01/07/09 0 0 01/07/09 CAP endorsed by gov 100% WB All activities covered under minimal constraints  
    Community meeting Hall 2 1 Infrastructure 04/02/09 05/04/10 425 60 04/06/10 Submission of Community Final Report 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 14/09/11 03/10/11 19 0 03/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    To be identified 3 2 Not Defined 24/10/11 21/08/12 302 6 27/08/12   0% SIDA - The field team were busy with the CAP consultations - Annex1 development & attachment preparation planned to kick off Monday 8th Nov 2011.
  Summary for Community: Garsoor 4 (5 detail records)
  Garsoor 5 School Extension 3 2 Education 13/10/10 22/12/10 70 0 22/12/10 Installment 1/3 Disbursed 0% DANIDA_RPLP -Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
    Community Action Plan Updated 3 2 CAP 11/05/11 11/05/11 0   11/05/11 CAP Endorsed by Goverment 100% DANIDA_RPLP    
  Summary for Community: Garsoor 5 (2 detail records)
  Horumar 1 Community Action Plan Updated 3 2 CAP 11/05/10 11/05/10 0   11/05/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Primary School (Extension) 3 2 Education 13/10/10 03/04/11 172 0 03/04/11 Installment 1/3 Disbursed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
  Summary for Community: Horumar 1 (2 detail records)
  Horumar 2 Community Action Plan 2 1 CAP 04/02/09 16/03/09 40 117 11/07/09 CAP endorsed by gov 100% WB    
    Health post 2 1 Health 12/08/09 29/04/10 260 62 30/06/10 Submission of Community Final Report 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 19/09/11 06/10/11 17 0 06/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    MCH Extension 3 2 Not Defined 31/10/11 23/09/12 328 0 23/09/12   0% SIDA All activities covered under minimal constraints  
  Summary for Community: Horumar 2 (5 detail records)
  Horumar 3 Village Water Drainage System (Sanitation) 3 2 Environment 01/11/10 07/03/11 126 0 07/03/11 Installment 1/3 Disbursed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
    Community Action Plan Updated 3 2 CAP 03/12/10 03/12/10 0   03/12/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
  Summary for Community: Horumar 3 (2 detail records)
  Israc 1 Community Action Plan 2 1 CAP 04/02/09 16/03/09 40 117 11/07/09 CAP endorsed by gov 100% WB    
    Community Center Repairs 2 1 Infrastructure 12/08/09 29/06/10 321 56 24/08/10 Submission of Community Final Report 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 18/09/11 11/10/11 23 0 11/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Football Pitch rehabilitation 3 2 Infrastructure 08/11/11 27/08/12 293 0 27/08/12   0% SIDA -Mobilization stage covered -Under Cap review & sector head functionality committee consultations  
  Summary for Community: Israc 1 (5 detail records)
  Israc 2 Community Action Plan Updated 3 2 CAP 07/10/10 17/10/10 10   17/10/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Community Market Place 3 2 Infrastructure 14/11/10 10/03/11 116 0 10/03/11 Installment 1/3 Disbursed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
  Summary for Community: Israc 2 (2 detail records)
  Israc 3 Community Action Plan Updated 3 2 CAP 21/10/10 07/11/10 17   07/11/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Construction of Marketplace 3 2 Infrastructure 14/11/10 10/03/11 116 0 10/03/11 MoU Signed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU Technical unit discussions.  
  Summary for Community: Israc 3 (2 detail records)
  Israc 4 Building an Assembly hall 2 1 Infrastructure 12/08/09 29/06/10 321 56 24/08/10 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan 2 1 CAP 05/02/09 17/03/09 40 117 12/07/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/11/10 356 0 01/11/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 21/09/11 16/10/11 25 0 16/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Market place 3 2 Infrastructure 08/11/11 27/08/12 293 0 27/08/12   0% SIDA    
  Summary for Community: Israc 4 (5 detail records)
  Israc 5 Community Action Plan Updated 3 2 CAP 23/11/10 24/11/10 1   24/11/10 CAP Endorsed by Goverment 100% DANIDA_RPLP    
    Construction of Intermediate and Primary School 3 2 Education 24/11/10 30/03/11 126 0 30/03/11 Installment 1/3 Disbursed 0% DANIDA_RPLP Withstanding due to Prolonged DRC Technical team & QAU  
  Summary for Community: Israc 5 (2 detail records)
  Rooh Construction of Primary shcool 2 1 Education 12/08/09 29/06/10 321 56 24/08/10 Completion and Acceptance of work 100% WB    
    Community Action Plan 2 1 CAP 25/03/09 04/05/09 40 41 14/06/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 10/11/09 01/06/10 203 0 01/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 21/09/11 16/10/11 25 0 16/10/11 CAP endorsed by Government 100% SIDA   - To upload the documents in late October and early November 2011
    Community Center 3 2 Infrastructure 21/11/11 06/08/12 259 0 06/08/12   0% SIDA   - Annex1 development & attachment preparation planned to kick off Monday 8th Nov 2011.
  Summary for Community: Rooh (5 detail records)
Summary for District: North_Galkayo (68 detail records)
Odweene Beerato 5 Berkads rehabilitation 0 0 Water Supply 11/01/12 11/01/12 0   11/01/12   0% Not Defined    
    Agro Store and supply of seeds and tools 1 3 Agriculture Extension 16/05/12           0% SIDA    
    Community Action Plan 2 1 CAP 03/01/09 14/02/09 42 0 14/02/09 CAP endorsed by gov 100% WB    
    Oxen for Farming 2 1 Agriculture Extension 14/09/09 30/06/10 289 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/11/10 406 0 11/11/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 26/07/11 28/08/11 33 0 28/08/11   100% SIDA No delay  
    Environment 3 2 Environment 26/06/12 17/09/12 83 0 17/09/12   5% SIDA    
  Summary for Community: Beerato (7 detail records)
  Dabagorayaale Rehabilitation of 4 barkats 2 1 Water Supply 16/05/09 16/02/10 276 0 16/02/10 Completion and Acceptance of work 100% WB    
    Community Action Plan 2 1 CAP 16/05/09 25/06/09 40 0 25/06/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 05/08/11 07/08/11 2 0 07/08/11   100% SIDA No delay  
    Community Center 3 2 Infrastructure 15/08/11 18/08/12 369 0 18/08/12   90% SIDA    
  Summary for Community: Dabagorayaale (5 detail records)
  Dheliwayn Barkats 2 1 Water Supply 01/10/09 30/04/10 211 0 30/04/10 Submission of Community Final Report 100% DANIDA_PLIS   Support discontinued
    Community Action Plan 2 1 CAP 13/09/11 30/01/09 -956 0 30/01/09 Drafted CAP 100% DANIDA_PLIS   Support discontinued
  Summary for Community: Dheliwayn (2 detail records)
  Eil Hume Health post 2 1 Health 12/04/09 07/03/10 329 0 07/03/10 Completion and Acceptance of work 100% WB    
    Community Action Plan 2 1 CAP 07/07/09 16/08/09 40 0 16/08/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    10 Latrines and provision of sanitation hand tools 2 1 Sanitation 01/11/09 26/09/10 329 0 26/09/10 Completion and Acceptance of work 100% WB    
    Community Action Plan Updated 3 2 CAP 18/08/11 20/08/11 2 0 20/08/11   100% SIDA No delay  
    Community Center 3 2 Infrastructure 25/08/11 14/08/12 355 0 14/08/12   10% SIDA    
  Summary for Community: Eil Hume (6 detail records)
  Gatiitalay Oxen for Farming 2 1 Agriculture Extension 24/04/09 15/10/10 539 0 15/10/10 Completion and Acceptance of work 100% DANIDA_PLIS   Support discontinued
    Social Services Access Grant 2 1 SAG 22/02/11     0     100% DANIDA_PLIS    
    Community Action Plan 3 0 Not Defined 01/09/09 01/10/09 30 0 01/10/09   0% Not Defined No site engineer to prepare BOQ with the community  
    Community Centre 3 2 Infrastructure 17/05/10 16/02/11 275 0 16/02/11 Completion and Acceptance of work 100% DANIDA_PLIS   Support discontinued
    Community Action Plan 3 2 CAP 11/05/10 15/06/10 35   15/06/10 CAP endorsed by gov 100% DANIDA    
  Summary for Community: Gatiitalay (5 detail records)
  Haahi                            
    Flood Protection 0 0 Water Supply 13/08/11 07/09/11 25   07/09/11   80% SIDA    
    Community Action Plan 2 1 CAP 11/04/09 21/05/09 40 0 21/05/09 CAP endorsed by gov 100% WB    
    Water Diversion 2 1 Water Supply 13/04/09 17/03/10 338 0 17/03/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 07/08/11 09/08/11 2 0 09/08/11   0% SIDA    
    Water Diversion 3 2 Water Supply 08/08/11 23/08/12 381 0 23/08/12   5% SIDA    
  Summary for Community: Haahi (7 detail records)
  Haaji Saalah Community Action Plan 2 1 CAP 13/04/09 23/05/09 40 0 23/05/09 CAP endorsed by gov 100% WB    
    Rehabilitation of 4 barkats 2 1 Water Supply 13/04/09 07/03/10 328 0 07/03/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community center 3 2 Infrastructure 30/08/11 27/09/12 394 0 27/09/12   90% SIDA    
    Community Action Plan Updated 3 2 CAP 28/08/11 30/08/11 2 0 30/08/11   100% SIDA NO delay  
  Summary for Community: Haaji Saalah (5 detail records)
  Haroshiekh Community Action Plan 2 1 CAP 11/04/09 21/05/09 40 0 21/05/09 CAP endorsed by gov 100% WB    
    School Extension 2 1 Education 11/04/09 07/03/10 330 0 07/03/10 Completion and Acceptance of work 100% WB No delay  
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 09/08/11 11/08/11 2 0 11/08/11   100% SIDA No delay  
    Community Center 3 2 Infrastructure 22/08/11 07/10/12 412 0 07/10/12   100% SIDA    
  Summary for Community: Haroshiekh (5 detail records)
  Khatumo Community Action Plan 2 1 CAP 15/04/09 25/05/10 405 0 25/05/10 CAP endorsed by gov 100% WB No site engineer to prepare BOQ with the community  
    Construction of MCH 2 1 Health 05/06/09 07/03/10 275 0 07/03/10 Submission of Community Final Report 100% WB No delay  
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 14/08/11 16/08/11 2 0 16/08/11   100% SIDA    
    Berkeds 3 2 Water Supply 08/08/11 22/09/12 411 0 22/09/12   5% SIDA    
  Summary for Community: Khatumo (5 detail records)
  Mulaho Community Action Plan 2 1 CAP 16/08/09 26/09/09 41 0 26/09/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Rehabilitation of 4 barkats 2 1 Water Supply 31/08/09 30/06/10 303 0 30/06/10 Completion and Acceptance of work 100% WB    
    Construction Of Community Center 3 0 Infrastructure 25/01/12 01/03/12 36   01/03/12   0% CDRD Grant    
    Community Center 3 2 Infrastructure 14/08/12 10/06/12 -65   10/06/12   10% SIDA    
    Community Action Plan Updated 3 2 CAP 17/08/11 19/08/11 2 0 19/08/11   100% SIDA    
  Summary for Community: Mulaho (6 detail records)
  Odweine Town Shallow wells 2 1 Agriculture Extension 12/05/09 27/01/10 260 0 27/01/10 Submission of Community Final Report 100% WB   Wells not yet functional due to technical problems
    Community Action Plan 2 1 CAP 09/05/09 18/06/09 40 0 18/06/09 CAP endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 08/08/11 10/08/11 2 0 10/08/11   100% SIDA    
    8 Shallow Wells 3 2 Water Supply 16/08/11 12/09/12 393   12/09/12   90% SIDA    
  Summary for Community: Odweine Town (5 detail records)
  Qaloocato Rehabilitation of 4 barkats 2 1 Water Supply 12/05/09 17/02/10 281 0 17/02/10 Completion and Acceptance of work 100% WB Completion and Acceptance of work  
    Community Action Plan 2 1 CAP 12/05/09 21/06/09 40 0 21/06/09 cap endorsed by gov 100% WB    
    Social Access Fund 2 1 SAG 01/10/09 11/04/10 192 0 11/04/10 Submission of Community Final Report 100% WB    
    Social Access Fund (Additional funding) 2 2 SAG 15/05/10 30/09/10 138 0 30/09/10 Installment 1/1 disbursed 100% WB    
    Community Center (Additional Funding) 2 2 Infrastructure 15/05/10 30/09/10 138 0 30/09/10 Completion and Acceptance of work 100% WB    
    Community Action Plan Updated 3 2 CAP 11/08/11 11/08/11 0 0 11/08/11   100% SIDA    
    Berkeds 3 2 Water Supply 11/08/11 03/09/12 389 0 03/09/12   5% SIDA    
  Summary for Community: Qaloocato (7 detail records)
Summary for District: Odweene (65 detail records)
Qardho Armo Social Access Fund 2 1 SAG 01/09/10 30/10/10 59 0 30/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Barkads 2 1 Water Supply 26/09/10     0   Installment 1/3 disbursed 0% DANIDA_RPLP   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Construction of School 3 2 Education 01/11/10 30/12/11 424 0 30/12/11 Installment 2/3 Disbursed 45% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Armo (4 detail records)
  Dhuudo Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Dhuudo (1 detail records)
  Garihel Social Access Fund 2 1 SAG 26/09/10     0   Submission of Community Final Report 100% DANIDA_RPLP    
    Water Catchments 3 2 Water Supply 14/11/10 30/12/11 411 0 30/12/11 Installment 2/3 Disbursed 50% DANIDA_RPLP No delay  
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Garihel (3 detail records)
  Guud Ad Block grant 0 1 Not Defined 05/04/12           0% Not Defined    
    Community Action Plan 3 1 CAP 05/04/12           0% DANIDA_2012    
  Summary for Community: Guud Ad (2 detail records)
  Habal-reer Social Access Fund 2 1 SAG 01/09/10 31/10/10 60 0 31/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Community Latrines 2 1 Infrastructure 26/09/10     0   Installment 1/3 disbursed 0% DANIDA_RPLP   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Communal Water Roof Chatchment 25 3 2 Water Supply 01/01/11 30/12/11 363 0 30/12/11 Installment 2/3 Disbursed 60% DANIDA_RPLP No delay  
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Habal-reer (4 detail records)
  Humbays Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Humbays (1 detail records)
  Jedad Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Jedad (1 detail records)
  Kaambo Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Kaambo (1 detail records)
  Kubo Social Access Fund 2 1 SAG 01/09/10 31/10/10 60 0 31/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Construction of School 3 2 Education 01/01/11 31/12/11 364 0 31/12/11 Installment 2/3 Disbursed 60% DANIDA_RPLP No delay  
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Kubo (3 detail records)
  Luba-har Social Access Fund 2 1 SAG 01/09/10 31/10/10 60 0 31/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Construction of School 3 2 Education 01/01/11 01/12/11 334 0 01/12/11 Installment 2/3 Disbursed 45% DANIDA_RPLP Disputes among the contractor and CPIU a raised during last three weeks due to in security and financial mismanagement  
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Luba-har (3 detail records)
  Rako Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Rako (1 detail records)
  Shahda Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Shahda (1 detail records)
  Shimbirale Social Access Fund 2 1 SAG 01/09/10 31/10/10 60 0 31/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Construction of Marketplace 2 1 Infrastructure 27/09/10     0   Installment 1/3 disbursed 0% DANIDA_RPLP   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Community Center 3 2 Infrastructure 01/01/11 01/12/11 334 0 01/12/11 Installment 1/3 Disbursed 0% DANIDA_RPLP    
    Community Action Plan Updated 3 2 CAP 13/06/11 07/06/11 -6   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Shimbirale (4 detail records)
  Shire Social Access Fund 2 1 SAG 01/09/10 31/10/10 60 0 31/10/10 Submission of Community Final Report 100% DANIDA_RPLP    
    Health Post 2 1 Health 27/09/10     0   Installment 1/3 disbursed 0% DANIDA_RPLP   - Due to a logistic and security problems the missing information will be uploaded in November 2011
    Construction of two Berkads 3 2 Water Supply 01/01/11 31/12/11 364 0 31/12/11 Installment 2/3 Disbursed 70% DANIDA_RPLP No delay  
    Community Action Plan Updated 3 2 CAP 01/01/11 07/06/11 157   07/06/11 CAP integrated into government plans 100% DANIDA_RPLP    
  Summary for Community: Shire (4 detail records)
  Yaka Block Grant 0 1 Not Defined 05/04/12           0% Not Defined    
  Summary for Community: Yaka (1 detail records)
Summary for District: Qardho (34 detail records)
Salahlay Adan abokor Community Action Plan 3 1 CAP 17/08/11 15/09/11 29 0 15/09/11   0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Berkad rehabilitation 3 1 Water Supply 09/09/11 27/02/12 171 0 27/02/12 Submission of Community Final Report 100% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Social Access Grant 3 1 SAG 00/00/00     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Adan abokor (3 detail records)
  Bahadhamal Community Action Plan 3 1 CAP 30/01/12     0     0% SIDA    
    Berkad rehabilitation 3 1 Water Supply 30/01/12           0% SIDA    
    Block Grant 3 1 Not Defined 00/00/00           0% SIDA    
  Summary for Community: Bahadhamal (3 detail records)
  Dhimbiriyaale Block Grant 3 1 Not Defined 30/01/12           0% SIDA    
    Community Action Plan 3 1 CAP 30/01/12     0     0% SIDA    
  Summary for Community: Dhimbiriyaale (2 detail records)
  Higlada Community Action Plan 3 1 CAP 28/08/11 10/11/11 74 0 10/11/11 Community Action Plan Drafted 0% DFID_II   CAPs to be uploaded January 2012
    Berkad rehabilitation 3 1 Water Supply 05/11/11 27/05/12 204 0 27/05/12 Completion and Acceptance of Work 100% DFID_II   CAPs with prioritized projects to be submitted January 2012
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Higlada (3 detail records)
  Ina Guxa Community Action Plan 3 1 CAP 16/10/11 11/11/11 26 0 11/11/11 CAP endorsed 100% DFID_II   CAPs to be uploaded January 2012
    Berkad rehabilitation 3 1 Water Supply 05/11/11 27/05/12 204 0 27/05/12 Installment 2/3 Disbursed 80% DFID_II   CAPs with prioritized projects to be submitted January 2012
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Ina Guxa (3 detail records)
  Ina Igare Community Action Plan 3 1 CAP 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Rehabilitation of barkeds 3 1 Water Supply 04/12/11 26/12/12 388 0 26/12/12   70% DANIDA_RPLP No site engineer to prepare BOQ with the community  
    Social Access Grant 3 1 SAG 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Ina Igare (3 detail records)
  Kam tuug Community Action Plan 3 1 CAP 15/10/11 10/11/11 26 0 10/11/11 CAP endorsed 100% DFID_II    
    Berkad rehabilitation 3 1 Water Supply 05/11/11 12/05/12 189 0 12/05/12 Completion and Acceptance of Work 100% DFID_II    
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Kam tuug (3 detail records)
  Qool aday Community Action Plan 3 1 CAP 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Rehabilitation of barkeds 3 1 Water Supply 28/08/11     0     0% DANIDA_RPLP No site engineer to prepare BOQ with the community  
    Social Access Grant 3 1 SAG 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Qool aday (3 detail records)
  Qool Bulale Community Action Plan 3 1 CAP 28/08/11     0     0% DANIDA_RPLP    
    Rehabilitation of five berkads 3 1 Water Supply 28/08/11     0     0% DANIDA_RPLP    
    Social Access Grant 3 1 SAG 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Community Action Plan 3 1 Water Supply 17/04/12           100% Not Defined    
  Summary for Community: Qool Bulale (4 detail records)
  Qool Dhuhulale Community Action Plan 3 1 CAP 15/10/11 10/11/11 26 0 10/11/11 Community Action Plan Drafted 0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Berkad rehabilitation 3 1 Water Supply 05/11/11 27/05/12 204 0 27/05/12 Installment 2/3 Disbursed 80% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Qool Dhuhulale (3 detail records)
  Raybadka Block Grant 3 1 Not Defined 30/01/12           0% SIDA    
    Community Action Plan 3 1 CAP 30/01/12     0     0% SIDA    
  Summary for Community: Raybadka (2 detail records)
  Salahlay 26 latrines 3 1 Sanitation 19/12/11 19/12/11 0   19/12/11   100% DANIDA_RPLP    
    Community Action Plan 3 1 CAP 28/08/11 15/09/11 18 0 15/09/11   0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
    Rehabilitation of four berkads 3 1 Water Supply 28/08/11 22/02/12 178 0 22/02/12 1/3 installment 0% DANIDA_RPLP Checked the QAU  
    Social Access Grant 3 1 SAG 28/08/11     0     0% DANIDA_RPLP   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Salahlay (4 detail records)
  Sharmarke Community Action Plan 3 1 CAP 05/11/11 30/11/11 25 0 30/11/11 CAP endorsed 100% DFID_II    
    Rehabilitation of berkads 3 1 Water Supply 05/11/11 10/07/12 248 0 10/07/12   100% DFID_II    
    Social Access Grant 3 1 SAG 28/08/11     0     0% DFID_II   Mobilization process has finished. PICD process and Filling annex one is on-going. The CD Coordinator will provide the activity plans soon
  Summary for Community: Sharmarke (3 detail records)
  Toon Block Grant 3 1 Not Defined 30/01/12           0% SIDA    
    Community Action Plan 3 1 CAP 30/01/12     0     0% SIDA    
  Summary for Community: Toon (2 detail records)
  Xadhid xadhig Berkad rehabilitation 3 1 Water Supply 30/01/12           0% SIDA    
    Community Action Plan 3 1 CAP 30/01/12     0     0% SIDA    
  Summary for Community: Xadhid xadhig (2 detail records)
Summary for District: Salahlay (43 detail records)
Sheikh Ala ule Community Action Plan 2 1 CAP 04/07/09 12/08/09 39 0 12/08/09 CAP reviewed by partners 100% WB    
    Irrigation canal extension 2 1 Agriculture Extension 18/11/09 30/06/10 224 0 30/06/10 Submission of Community Final Report 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 Not Defined 20/11/11 20/01/12 61   20/01/12 CAP updated 100% DFID_II    
    Health Post 3 2 Health 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Ala ule (5 detail records)
  Dariko Community Action Plan 2 1 CAP 04/07/09 12/08/09 39 0 12/08/09 CAP endorsed by gov 100% WB    
    Water Extension 2 1 Water Supply 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB   Though the subproject is completed the water tank is still not able to receive water and possible reasons given by the community is the general water shortage in Shiekh town. The CDC will discuss the issue with the Mayor who was highly involved in the implementation of the subproject.
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    School gate and Generator room 3 2 Education 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Dariko (5 detail records)
  Girni Community Action Plan 2 1 CAP 19/08/09 28/09/09 40 0 28/09/09 CAP endorsed by gov 100% WB    
    Construction of primary school 2 1 Education 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Berked construction 3 2 Water Supply 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Girni (5 detail records)
  Guguh Community Action Plan 2 1 CAP 04/07/09 12/08/09 39 0 12/08/09 CAP endorsed by gov 100% WB    
    Health post 2 1 Health 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB   The health posts is operational with staff and medicines available and functions more like an MCH. The CD Coordinator described it as "busy" during her field visit in July 2010.
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    School gate and Dining room 3 2 Education 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Guguh (5 detail records)
  Himan Community Action Plan 2 1 CAP 25/10/09 31/12/09 67 0 31/12/09 CAP endorsed by gov 100% WB    
    Agriculture extension (Oxen farming) 2 1 Agriculture Extension 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/12/11 20/01/12 31   20/01/12 CAP endorsed 0% DFID_II    
    School gate, kitchen and dining room 3 2 Education 01/01/12 30/09/12 273 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Himan (5 detail records)
  Hulqaboobe Community Action Plan 2 1 CAP 09/09/09 04/10/09 25 0 04/10/09 PICD Completed (CAP drafted) 100% WB    
    Health post 2 1 Health 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB   Staff already trained to work in the health post
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Flood Protection Wall 3 2 Infrastructure 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Hulqaboobe (5 detail records)
  Kulmiye Community Action Plan 2 1 CAP 30/11/09 30/12/09 30 0 30/12/09 CAP endorsed by gov 100% WB    
    Road rehabilitation 2 1 Infrastructure 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 24/03/10 105 0 24/03/10 Submission of Community Final Report 100% WB    
    Social Access Fund (Additional Funding) 2 2 SAG 15/05/10 30/09/10 138 0 30/09/10 Submission of Community Final Report 100% WB    
    Health post (additional funding) 2 2 Health 15/05/10 30/09/10 138 0 30/09/10 Completion and Acceptance of work 100% WB   Staff already trained to work in the health post
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Irrigation Canal and Water Pumps 3 2 Water Supply 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Kulmiye (7 detail records)
  Sheikh Dayaha Community Action Plan 2 1 CAP 30/09/09 03/10/09 3 0 03/10/09 CAP endorsed by gov 100% WB    
    Bridge and water diversion 2 1 Infrastructure 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Latrines 3 2 Sanitation 21/01/12 30/09/12 253 0 30/09/12 Completion and Acceptance of Work 40% DFID_II    
  Summary for Community: Sheikh Dayaha (5 detail records)
  Sheikh Nuura Community Action Plan 2 1 CAP 04/07/09 12/08/09 39 0 12/08/09 CAP endorsed by gov 100% WB    
    Construction of Community Center 2 1 Infrastructure 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Transport bridge and foot bridge 3 2 Infrastructure 21/01/12 30/09/12 253 0 30/09/12 Installment 2/3 Disbursed 80% DFID_II    
  Summary for Community: Sheikh Nuura (5 detail records)
  Suqsade Community Action Plan 2 1 CAP 04/07/09 12/08/09 39 0 12/08/09 CAP endorsed by gov 100% WB    
    Agriculture Extension 2 1 Agriculture Extension 18/11/09 30/06/10 224 0 30/06/10 Completion and Acceptance of work 100% WB    
    Social Access Fund 2 1 SAG 09/12/09 30/06/10 203 0 30/06/10 Submission of Community Final Report 100% WB    
    Community Action Plan Updated 3 2 CAP 20/11/11 20/01/12 61   20/01/12 CAP endorsed 0% DFID_II    
    Community Centre 3 2 Infrastructure 15/01/12 15/03/12 60 0 15/03/12 Completion and Acceptance of Work 100% DFID_II    
  Summary for Community: Suqsade (5 detail records)
Summary for District: Sheikh (52 detail records)
South_Galkayo Alanleey Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 190 10/06/10 CAP Endorsed by gov 100% DANIDA    
    Community Center 2 1 Infrastructure 31/12/09 15/08/10 227 180 11/02/11 Completion and Acceptance of work 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/12/09 15/08/10 227 180 11/02/11 Submission of Community Final Report 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 11/09/11 04/10/11 23   04/10/11 CAP updated 0% SIDA    
    Block Grant 3 2 Not Defined 04/10/11 04/06/12 244   04/06/12   0% SIDA    
  Summary for Community: Alanleey (5 detail records)
  Arafaat Community Action Plan 2 1 CAP 21/11/09 14/12/09 23 86 10/03/10 CAP endorsed by gov 100% DANIDA    
    Community Center 2 1 Infrastructure 31/12/09 15/08/10 227 123 16/12/10 Completion and Acceptance of work 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/12/09 15/08/10 227 123 16/12/10 Submission of Community Final Report 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 11/09/11 04/10/11 23   04/10/11   0% SIDA    
    Block Grant 3 2 Not Defined 04/10/11 04/10/11 0   04/10/11   0% SIDA    
  Summary for Community: Arafaat (5 detail records)
  Arfuuda Community Action Plan 2 1 CAP 16/11/09 26/12/09 40 93 29/03/10 CAP endorsed by gov 100% DANIDA    
    Berkad Construction 2 1 Water Supply 31/12/09 15/08/10 227 123 16/12/10 Completion and Acceptance of work 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/12/09 15/08/10 227 123 16/12/10 Submission of Community Final Report 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 09/09/11 11/10/11 32   11/10/11   0% Not Defined    
    To be identified 3 2 Not Defined 08/12/11 11/06/12 186   11/06/12   0% Not Defined    
  Summary for Community: Arfuuda (5 detail records)
  Bandiradlay Community Action Plan 3 1 CAP 02/10/10 17/11/10 46   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 01/12/10 31/05/11 181 0 31/05/11 Completion and Acceptance of Work 100% DFID No delay  
    Social Services Access Grant 3 1 SAG 01/12/10 10/05/11 160 0 10/05/11 Installment 1/1 Disbursed 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 28/11/11 22/01/12 55   22/01/12 CAP endorsed 0% DFID_II    
    Block Grant 3 2 Not Defined 31/01/12           0% DFID_II    
  Summary for Community: Bandiradlay (5 detail records)
  Bitaale Community Action Plan 3 1 CAP 26/10/10 17/11/10 22   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 26/12/10 31/05/11 156 0 31/05/11 Completion and Acceptance of Work 100% DFID There is No delay according to the submitted report. there are no actions taken and Successfully completed.
    Social Services Access Grant 3 1 SAG 26/12/10 10/05/11 135 0 10/05/11 Submission of Community Final Financial Report 100% DFID    
    Community Action Plan Updated 3 2 CAP 28/11/11 10/11/12 348   10/11/12 CAP endorsed 0% DFID_II    
    Block Grant 3 2 Not Defined 31/01/12           0% DFID_II    
  Summary for Community: Bitaale (5 detail records)
  Dagari Community Action Plan 3 1 CAP 02/10/10 17/11/10 46   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Construction of MCH 3 1 Health 18/11/10 14/03/11 116 42 25/04/11 Installment 3/3 Disbursed 100% DFID QAU delay of approval  
    Social Services Access Grant 3 1 SAG 21/11/10 10/05/11 170 0 10/05/11 Installment 1/1 Disbursed 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 06/12/11 18/01/12 43   18/01/12 CAP endorsed 0% DFID_II    
    Block Grant 3 2 Not Defined 31/01/12           0% DFID_II    
  Summary for Community: Dagari (5 detail records)
  Dalsan Community Action Plan 2 1 CAP 18/10/09 27/11/09 40 94 01/03/10 CAP revised by communities 100% WB    
    Community Center 2 1 Infrastructure 31/12/09 15/08/10 227 123 16/12/10 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/12/09 15/08/10 227 123 16/12/10 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 28/09/11 29/09/11 1   29/09/11   0% SIDA    
    Block Grant 3 2 Not Defined 25/10/11 03/06/12 222   03/06/12   0% SIDA    
  Summary for Community: Dalsan (5 detail records)
  Docol Community Action Plan 3 1 CAP 16/10/10 17/11/10 32   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Community Center 3 1 Infrastructure 09/01/11 31/05/11 142 0 31/05/11 Completion and Acceptance of Work 100% DFID Project completion date delayed due to conflict between the contractor and committee that cause to give more time to solve their problem and with the support of district authority but unfornately they fail and we referred to local authority to solve.  
    Social Services Access Grant 3 1 SAG 09/01/11 10/05/11 121 0 10/05/11 Installment 1/1 Disbursed 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 30/11/11 12/01/12 43   12/01/12 CAP endorsed 100% DFID_II    
  Summary for Community: Docol (4 detail records)
  Galbarwaqo Community Action Plan 3 1 CAP 16/10/10 17/11/10 32   17/11/10 CAP Endorsed by Goverment 100% DFID    
    Construction of MCH 3 1 Health 12/12/10 31/05/11 170 0 31/05/11 Completion and Acceptance of Work 100% DFID There is no delay  
    Social Services Access Grant 3 1 SAG 12/12/10 13/01/11 32 0 13/01/11 Installment 1/1 Disbursed 100% DFID   - Due to a logistic and security problems the missing information will be uploaded in October 2011
  Summary for Community: Galbarwaqo (3 detail records)
  Galinsoor Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 83 23/02/10 PICD Completed (CAP drafted) 100% DANIDA    
    marketplace 2 1 Infrastructure 31/12/09 15/08/10 227 123 16/12/10 Completion and Acceptance of work 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/12/09 15/08/10 227 123 16/12/10 Submission of Community Final Report 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 14/10/11 15/10/11 1   15/10/11   0% SIDA    
    Block Grant 3 2 Not Defined 18/12/11 13/06/12 178   13/06/12   0% SIDA    
  Summary for Community: Galinsoor (5 detail records)
  Midnimo To be identified 0 0 Not Defined 25/11/11 05/06/12 193   05/06/12   0% Not Defined    
    Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 107 19/03/10 CAP endorsed by gov 100% WB    
    Community Center 2 1 Infrastructure 31/01/10 30/09/10 242 175 24/03/11 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/01/10 30/09/10 242 175 24/03/11 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 05/09/11 19/09/11 14   19/09/11   0% SIDA    
  Summary for Community: Midnimo (5 detail records)
  Qodah-toole Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 106 18/03/10 CAP endorsed by gov 100% WB    
    Maternal and Child Health center 2 1 Health 31/01/10 30/09/10 242 175 24/03/11 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/01/10 30/09/10 242 175 24/03/11 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Center (Additional Funding) 2 1 Infrastructure 06/02/11     0   Completion and Acceptance of Work 100% WB No delay  
    Social Services Access Grant (Additional Fund) 2 1 SAG 06/02/11     0   Installment 1/1 Disbursed 100% DANIDA_RPLP   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 09/10/11 24/10/11 15   24/10/11   0% DFID_II    
    Block Grant 3 2 CAP 08/12/11 11/06/12 186   11/06/12   0% SIDA    
  Summary for Community: Qodah-toole (7 detail records)
  Sadah-higlo Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 90 02/03/10 CAP endorsed by gov 100% DANIDA    
    School Construction 2 1 Education 31/01/10 30/09/10 242 175 24/03/11 Completion and Acceptance of work 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/01/10 30/09/10 242 175 24/03/11 Submission of Community Final Report 100% DANIDA   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 12/10/11 24/10/11 12   24/10/11   0% SIDA    
    Block Grant 3 2 Not Defined 18/12/11 13/06/12 178   13/06/12   0% SIDA    
  Summary for Community: Sadah-higlo (5 detail records)
  Waaberi Community Action Plan 2 1 CAP 21/11/09 02/12/09 11 75 15/02/10 CAP endorsed by gov 100% WB    
    Community Center 2 1 Infrastructure 31/01/10 30/09/10 242 175 24/03/11 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/01/10 30/09/10 242 175 24/03/11 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 29/09/11 17/10/11 18   17/10/11   0% SIDA    
    Block Grant 3 2 Not Defined 05/11/11 03/06/12 211   03/06/12   0% SIDA    
  Summary for Community: Waaberi (5 detail records)
  Wargalo To be identified 0 0 Not Defined 25/11/11 07/06/12 195   07/06/12   0% Not Defined    
    Community Action Plan 2 1 CAP 16/11/09 26/12/09 40 95 31/03/10 CAP endorsed by gov 100% WB    
    Health Post 2 1 Health 31/01/10 30/09/10 242 175 24/03/11 Completion and Acceptance of work 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Social Access Fund 2 1 SAG 31/01/10 30/09/10 242 175 24/03/11 Submission of Community Final Report 100% WB   - Due to a logistic and security problems the missing information will be uploaded in October 2011
    Community Action Plan Updated 3 2 CAP 06/10/11 19/10/11 13   19/10/11   0% SIDA    
  Summary for Community: Wargalo (5 detail records)
Summary for District: South_Galkayo (74 detail records)
Grand Total (688 detail records)
Page  First Previous Next Last  of 1
     Records 1 to 13 of 13      Groups per page 


 ©2011 SOMCDRD.ORG. All rights reserved.